On 29 May 2013, the Petroleum Safety Authority Norway (PSA) carried out an audit of ConocoPhillips Skandinavia AS (ConocoPhillips)'s new wellhead platform, 2/4 Z, on Ekofisk within the technical disciplines of process safety and electrical installations.


Ekofisk 2/4 Z will be an extension of the Ekofisk complex and connected to the process facility at 2/4 J via a gangway connection to 2/4 M. It will have a total of 36 well slots, of which 35 can be used for production wells, while one slot will be used for cuttings reinjection.

Objective
The objective of the audit was to verify that Ekofisk 2/4-Z has been built in accordance with regulatory requirements within the technical disciplines of process safety and electrical installations.

Result
No non-conformities or improvement points were identified.

Journal 2012/611

 