Audit of Det Norske's follow-up of the Ivar Aasen project

The Petroleum Safety Authority Norway (PSA) has carried out an audit of Det Norske's follow-up of the Ivar Aasen project in respect of the company's and main contractor's project management.


The objective of the audit was to assess whether Det Norske's management of emergency preparedness, materials handling and OHAS complies with the regulatory requirements.

Result
One non-conformity was identified in connection with the documentation for cranes.

In addition, three improvement points were identified in connection with:

  • Access to overhead cranes
  • The materials handling plan
  • Location of the emergency hospital

Det Norske has been given a deadline of 21 December 2015 to report on how the non-conformity and improvement points will be dealt with.

Non-conformity:
Entails that a condition is assessed as not complying with a regulatory requirement.

Improvement point:
Entails that we have identified a deficiency or weakness, without there being sufficient grounds for determining a breach of regulatory requirements.



 