Gå til hovedinnhold

Audit of environmental data collection at Draugen

From 8 to 10 June 2016, the PSA, together with the Norwegian Meteorological Institute, carried out an audit of the operator's management of environmental data collection at Draugen.


The objective of the audit was to review relevant routines for performing, maintaining and reporting the collection of environmental data and to assess the technical standard of systems and equipment at Draugen.

No non-conformities or improvement points were identified.

Non-conformity:
Entails that a condition is assessed as not complying with a regulatory requirement.

Improvement point:
Entails that we have identified a deficiency or weakness, without there being sufficient grounds for determining a breach of regulatory requirements.

Eileen Brundtland, Press contact
Email: eileen.brundtland@ptil.no | +47 51 87 35 12