From 19 to 21 June 2018, we carried out an audit of Equinor Energy AS (Equinor) and its follow-up of the working environment on the Martin Linge FSO.


Objective
The objective of the audit was to assess whether the Martin Linge FSO in operation satisfies the working environment requirements as

set out in the regulations.

Result
No non-conformities were identified.

Two improvement points were identified in connection with:

  • Assessment of health risks
  • Competence

Equinor has been given a deadline of 17 July 2018 to report on how the improvement points will be addressed.