Audit of Ivar Aasen field development

The PSA has carried out an audit of Det norske oljeselskap (Det norske) and the Ivar Aasen development project concerning project management and pipeline fabrication.


The objective of the audit was to assess whether Det norske is implementing the HSE regulations and its own requirements for pipeline fabrication.

Result
No non-conformities were identified.

Three improvement points were identified in connection with:

  • Documentation
  • Qualifications and competence
  • Follow-up

Det norske has been given a deadline of 10 July 2015 to report on how the improvement points will be dealt with.


Non-conformity:
Entails that a condition is assessed as not complying with a regulatory requirement.

Improvement point:
Entails that we have identified a deficiency or weakness, without there being sufficient grounds for determining a breach of regulatory requirements.

 

 

 