Audit of Norske Shell – Nyhamna

From 27 to 30 April 2015, the PSA carried out an audit of the management of health, safety and the environment (HSE) relating to the planning and performance of scaffolding work at Nyhamna.


The objective of the audit was to assess how Norske Shell (Shell) is monitoring and organising the prudent planning and performance of the scaffolding work.

Result
Non-conformities were identified in connection with:

  • Checking of scaffolding
  • Training
  • The supervisory duty
  • The safety service

No improvement points were identified.

Shell has been given a deadline of 7 August 2015 to report on how the non-conformities will be dealt with.


Non-conformity:
Entails that a condition is assessed as not complying with a regulatory requirement.

Improvement point:
Entails that we have identified a deficiency or weakness, without there being sufficient grounds for determining a breach of regulatory requirements.

 

 