Audit of Statoil and Maersk Drilling Norge AS – Maersk Gallant

Between 16 and 20 March 2015, the PSA carried out an audit of Statoil and Maersk Drilling concerning HPHT drilling operations at the 2/4-22 Romeo and 2/4-23 Julius exploration wells using Maersk Gallant.


The objective of the audit was to verify Statoil and Mærsk Drilling's planning, experience transfer and execution of high pressure, high temperature exploration drilling of the Romeo and Julius exploration wells.

Result
Non-conformities were identified in connection with:

  • Working environment committee
  • Working environment measures

In addition, improvement points were identified in connection with:

  • Installations, systems and equipment
  • Competence
  • Barriers

Statoil and Mærsk Drilling have been given a deadline of 01 August 2015 to report on how the non-conformities and improvement points will be dealt with.


Non-conformity:
Entails that a condition is assessed as not complying with a regulatory requirement.

Improvement point:
Entails that we have identified a deficiency or weakness, without there being sufficient grounds for determining a breach of regulatory requirements.