Audit of Statoil – Åsgard subsea compression project

On 28 May 2015, the Petroleum Safety Authority Norway carried out an audit of the Åsgard subsea compression project.


The objective of the audit was to obtain an update and status for the project and to verify that it is being planned and executed in compliance with the regulatory requirements.

Result
No non-conformities were identified.

An improvement point was identified in connection with the maintenance programme.

Statoil has been given a deadline of 25 September 2015 to report on how the improvement point will be dealt with.

Non-conformity:
Entails that a condition is assessed as not complying with a regulatory requirement.

Improvement point:
Entails that we have identified a deficiency or weakness, without there being sufficient grounds for determining a breach of regulatory requirements.


 