Audit of Statoil – detailed engineering of Polarled

From 11 to 12 March 2014, the Petroleum Safety Authority Norway (PSA) carried out an audit of detailed engineering of the Polarled pipeline.


Objective
The objective of the audit was to monitor that the project has been planned and carried out in compliance with applicable regulations and recognised norms, and that requirements in the HSE regulations are provided for.

Result
No non-conformities were identified.

Four improvement points were identified in connection with:

  • Document management
  • Design documentation
  • Free span analyses
  • Verification of software

 

Journal 2014/219

 