Audit of Statoil – Gina Krog

On 25 and 26 March 2015, the Petroleum Safety Authority Norway carried out an audit of the design engineering of structures and maritime systems for Gina Krog.


The objective of the audit was to verify that Statoil's analyses and verifications comply with the regulations.

Result
No non-conformities were identified.

Three improvement points were identified in connection with:

Verification of analyses
Structural analyses
Non-conformity handling

Statoil has been given a deadline of 10 June 2015 to report on how the improvement points will be dealt with.

Non-conformity:
Entails that a condition is assessed as not complying with a regulatory requirement.

Improvement point:
Entails that we have identified a deficiency or weakness, without there being sufficient grounds for determining a breach of regulatory requirements.