Audit of Statoil – Gullfaks C

From 3 to 6 December 2013, the Petroleum Safety Authority Norway (PSA) carried out an audit of the Gullfaks C facility.


Objective
The objective of the audit was to verify that Statoil's management and follow-up of barriers complied with the company's and the authorities' requirements.

Result
Non-conformities were identified in connection with:

  • risk analysis
  • reduction of explosion risks
  • evacuation routes

In addition, improvement points were identified in connection with:

  • strategies and principles for the design and use of barriers
  • area risk charts
  • risk analyses
  • performance of planned activities
  • monitoring and control
  • updating of operating documents
  • lifting equipment


Journal 2013/1298

 

 