From 11 to 13 June 2014, the Petroleum Safety Authority Norway (PSA) carried out an audit of electrical installations at Tjeldbergodden.


Objective
The objective of the audit was to evaluate planning, execution and follow-up of activities in relation to regulatory requirements.

Result
One non-conformity was identified in connection with safety measures when working on disconnected systems.

In addition, an improvement point was identified in connection with documentation.

 

 

 

 


 

Øyvind Midttun, Press contact