Audit of the management of emergency preparedness at Snorre A

Between 25 and 28 April 2016, the PSA carried out an audit of Statoil Petroleum AS (Statoil)'s management of emergency preparedness at Snorre A.


The objective was to review and assess how Statoil's streamlining processes are helping to ensure that robust emergency preparedness is part of the company's overall risk picture.

Result
No non-conformities or improvement points were detected during this audit.

Non-conformity:
Entails that a condition is assessed as not complying with a regulatory requirement.

Improvement point:
Entails that we have identified a deficiency or weakness, without there being sufficient grounds for determining a breach of regulatory requirements.