Audit of the Martin Linge development project within barriers and maintenance

From 2 to 9 May 2018, we carried out an audit of the management of barriers and maintenance for the Martin Linge production unit (PU) project in the completion phase at the Rosenberg yard, and the assembly and commissioning phase on the field.


Objective
The objective of the audit was to assess how Equinor Energy AS (Equinor) is ensuring compliance with statutory regulations and its own requirements for the management of major accident risk, barriers and maintenance in the completion and commissioning of the Martin Linge PU.

Result
No non-conformities were identified.

Improvement points were identified in connection with:

  • Preservation procedures
  • Temporary equipment
  • Heating cable installations
  • Labelling

Equinor has been given a deadline of 17 August 2018 to report on how the improvement points will be addressed.