Audit of verification of the engineering of Johan Sverdrup

On 27 and 28 April 2016, the PSA carried out an audit of Statoil. This activity was linked to the verification of load-bearing structures in the Johan Sverdrup RP project.


We wanted to perform spot checks at an early stage of whether the set-up for verification complied with the Facilities Regulations, Section 56 concerning load-bearing structures and NORSOK N-001 item 5.2.

Result
No non-conformities were detected during this audit.

An improvement point was identified concerning the control of analyses.

Statoil has been given a deadline of 11 June 2016 to report on how the improvement point will be dealt with.
 

 

Non-conformity:
Entails that a condition is assessed as not complying with a regulatory requirement.

Improvement point:
Entails that we have identified a deficiency or weakness, without there being sufficient grounds for determining a breach of regulatory requirements.

Eileen Brundtland, Press contact