Consent to carry out drilling with Scarabeo 8

Eni Norge AS has received consent to carry out drilling with the Scarabeo 8 mobile drilling facility.


The consent relates to the drilling of appraisal well 7122/7 – Goliat, which is part of production licence 229.

Water depth at the site is 382 metres.

The operation has an estimated duration of 50 days.

 

 