Gå til hovedinnhold

Consent to conduct permanent plugback, drilling and completion with COSLPioneer on Glitne

Statoil has been granted consent to use the mobile drilling facility COSLPioneer.


The consent applies to permanent plugback, drilling and completion of well 15/5 A-7, which is part of production licence 048 B. 

The planned position of the rig in connection with drilling and completion of 15/5-A-7 AH is:

N 58°43'30.301" 
E 1°38'25.419" 

Water depth at the site is approximately 110 metres.

Anticipated start-up of the operation is 29 February 2012. The activity is estimated to last for approximately 106 days.
 

 

COSLPioneer is a semi-submersible drilling installation of the type GM 4000D operated by COSL Drilling Europe AS.

Link: COSL Drilling has received an Acknowledgement of Compliance for COSLPioneer

Øyvind Midttun, Press contact
Email: oyvind.midttun@ptil.no | +47 51 87 34 77