Statoil Petroleum AS (Statoil) has received consent to use West Venture for completion of well 35/11-A-3 in the Fram H-Nord field.


Statoil has received consent from the Petroleum Safety Authority Norway (PSA) to use the West Venture mobile facility for completion of well  35/11-A-3 in the Fram H-Nord field in production licence 090.

Planned start-up of the operation is 28 March 2014, with a duration of approx. 23 days.

West Venture (photo) is a fifth-generation semi-submersible facility of the Kværner Maritime KMAR CS-45 design, equipped with dynamic positioning. The facility is fitted with two derricks.

West Venture is operated by Seadrill Offshore AS. The facility received Acknowledgement of Compliance (AoC) in January 2004.
 

Journal 2014/116

Øyvind Midttun, Press contact