Objective
The objective of the audit activity in this phase of the project is assessing whether Total’s and Technips’ management of the working environment, material handling and emergency preparedness in the Martin Linge development in the engineering phase is sufficient to ensure compliance with applicable management requirements in the relevant project phase.
Result
No nonconformities were identified.
Improvement items were identified in connection with:
Letter to Total E&P Norge (In Norwegian)
Audit report – Martin Linge-prosjektet (In Norwegian)
Journal 2013/233