Gå til hovedinnhold

Consent to modifications at Kollsnes

Gassco AS (Gassco) has received consent to install a new compressor and a new condensate train in connection with the "Kollsnes Flash Gas and Condensate Project" (KFGC).


The primary purpose of the KFGC project is to secure capacity to process future flash gas and condensate volumes when the new facilities commence operation at the end of 2008.

Kollsnes (kilde: Gassco)

The Kollsnes process facility (source: Gassco)

At the same time, the project will contribute to an improvement in the regularity and robustness of the Kollsnes process facility (pictured), particularly in connection with maintenance work on the compressors.

Contact person in the Petroleum Safety Authority Norway:
Mike Theiss