Consent to use Island Constructor

Consent: StatoilHydro has been granted consent for the use of Island Constructor to install conductor pipes in exploration well 35/2-2.


StatoilHydro has applied for consent to conduct exploration drilling of well 35/2-2 in production licenses 318 and 269 with the mobile facility Transocean Winner.

In the first stage of this drilling activity, the company wants the construction vessel Island Constructor to install conductor pipes in the well.

Island Constructor

M/V Island Constructor is owned by Island Offshore, and is built at Ulstein Verft.

StatoilHydro has applied for exemption from the requirement that mobile facilities conducting  petroleum activities on the Norwegian Shelf must have an Acknowledgement of Compliance (AoC).

Pursuant to Section 59 of the regulations relating to health, safety and the environment in the petroleum activities (the Framework Regulations), we have granted exemption from Section 17, third paragraph relating to health, safety and the environment in the petroleum activities regarding Acknowledgement of Compliance, for the purpose of installing conductor pipes in well 35/2-2, cf. Section 6, letter m of the Regulations relating to material and information in the petroleum activities.

From a risk-based approach, we accept such  a simplified solution for this limited activity. It is assumed that the restrictions and compensating measures which are  described in the information received  from StatoilHydro are complied with and/or implemented.

The exemption is valid from 10 April 2009 to 31 May 2009.