Order to Odfjell following audit of maintenance management

During the period 10 March to 12 March 2009, the Petroleum Safety Authority Norway (PSA) conducted an audit of Odfjell Drilling AS’ (ODAS) maintenance management. Based on our findings, the PSA has issued an order for ODAS in accordance with the previously issued notice.


Link: Notice of order following audit of Odfjell Drilling’s maintenance management system

We have issued ODAS an order to prepare a binding plan with set dates to ensure that the necessary maintenance is carried out.

The order is as follows:

Pursuant to Section 58 of the Framework Regulations, relating to administrative decisions, cf. Chapter IX of the Activities Regulations relating to maintenance, cf. Section 13 of the Management Regulations, relating to general requirements for analyses, Odfjell Drilling AS is ordered to prepare a binding plan with set dates to ensure that the necessary maintenance is carried out, including classification, preparation of a maintenance program and measurement of maintenance efficiency on all facilities for which Odfjell Drilling AS is responsible, both permanent and mobile.

The deadline to comply with the order has been set at 15 May 2009. We must be notified when the order has been complied with.