Summary of audit - Gjøa well solutions

On 30 April 2008 the Petroleum Safety Authority Norway (PSA) conducted an audit of StatoilHydro’s management of the Gjøa project in the well safety area. We did not find any non-conformities with the regulatory requirements.


Gjøa
Gjøa was proven in 1989 and is located about 40 km north of the Fram field. The reservoir contains gas above a relatively thin oil zone.

Location of GjøaStatoilHydro is the operator during the development phase, while Gaz de France will assume operator responsibility when the field comes on stream.

The development will comprise five subsea templates tied in to a semi-submersible production and process facility (illustration).
 
The oil will be exported in a new 55-km pipeline to be connected to Troll Oljerør II, for further transport to Mongstad.

The plan is to export the gas in a new 130-km pipeline to FLAGS-transport system on the British Continental Shelf, for onward transport to St. Fergus. The PDO was submitted in December 2006.

Audit
The audit was conducted as a meeting where the project organisation presented key topics linked to well solutions for Gjøa. Representatives from the development operator StatoilHydro and the future operator Gaz de France participated in the meeting.