On 27 September 2010, the Petroleum Safety Authority Norway (PSA) carried out an audit of the Yme facility related to the technical discipline process integrity.


The Yme facility is currently moored at Rosenberg shipyard in Stavanger, and the audit was carried out as part of the processing of the operator Talisman Energy Norge's application for consent to use the Yme facility.

Several technical disciplines carried out the supervision of Yme, and will report separately. This report concerns the results from process integrity. The audit emphasised following up the reports from previous audits, Talisman's reply and a verification round on board the facility.

Result
Most of the issues from previous audits have now been improved. Still, in a few areas, some issues still remain to be improved. The findings are not classified as nonconformities or improvement items.